Nuclear Technology – EPR (European Pressurized Reactor / Evolutionary Power Reactor)

Satisfied customers are our best recommendation! Here you will find a selection of our projects, which reflect the comprehensive range of services of MF Engineering.

Nukleartechnik – Kernkraftanlage Olkiluoto 3 – Pool Liner

New development of two steel halls for temporary enclosure of the reactor pools during the assembly period

Auftraggeber: Babcock Noell GmbH
Leistung: Structural calculation of the halls acc. to DIN 18800 each comprising of two parts with removable roof elements which can be lifted into the building with the crane
Nukleartechnik – Kernkraftanlage Olkiluoto 3 – Containment Liner

New development of the containment building of a Finnish power plant (height 65m, diameter 46m)

Auftraggeber: Babcock Noell Nuclear, Babcock Noell GmbH
Leistung: Participation with the structural design of assembly situations acc. to DIN 18800 and lining structures acc. to ASME
Kein Bild vorhanden.

New development of a water tank pool for a Finnish power plant (height 4m, diameter 33m)

Auftraggeber: Babcock Noell Nuclear, Babcock Noell GmbH
Leistung: Participation with the structural design of the steel structures and lining structures acc. to KTA (with earthquake loading and accidental temperature increase)
Nukleartechnik – Kernkraftanlage Olkiluoto 3 – Turbinengebäude

New development of the turbine building of a Finnish power plant

Auftraggeber: Siemens AG, Power Generation Division
Leistung: Check of structural calculations of steel support structures for pipelines and tanks acc. EN 1993-1 and Finnish NA
Nukleartechnik – Kernkraftanlage Olkiluoto 3 – Pool Liner

New development of two structures for the reactor pools of a Finnish power plant (height 10m, base area 260m²)

Auftraggeber: Babcock Noell Nuclear, Babcock Noell GmbH
Leistung: Participation with the structural design of steel structures and lining structures acc. to KTA (incl. earthquake loading)
Nukleartechnik – Kernkraftanlage Flamanville – Beckenauskleidungen

New development of a power plant in France

Auftraggeber: Babcock Noell GmbH
Leistung: Structural analysis of sealing doors, access doors and man holes in different pools and tanks with earthquake loading acc. to EC3
Nukleartechnik – Kernkraftanlage Olkiluoto 3 – Personenschleuse

New development of a personnel air lock for a Finnish power plant

Auftraggeber: Babcock Noell GmbH
Leistung: Structural design of a temporary support structure hung up at anchor plates for the assembly of the personnel air lock (approx. 34 t) acc. to DIN 18800
Nukleartechnik - Kernkraftanlage Olkiluoto 3 – Tank Liner

New development of six tanks for fluids for a Finnish power plant (height 2.8-4.5m, base area 8.5-15.3m²)

Auftraggeber: Babcock Noell GmbH
Leistung: Participation with the structural design of the lining structures acc. to KTA (with accidental temperature increase)
Kein Bild vorhanden.

New development of a power plant in China

Auftraggeber: Babcock Noell GmbH
Leistung: Structural analysis of sealing doors and access doors as well as a filter exchange machine with earthquake loading

New development of technical parts on top of the reactor closure head of a Finnish power plant

Auftraggeber: Babcock Noell Nuclear, Babcock Noell GmbH
Leistung: Participation with the structural design of technical steel structures acc. to KTA (with earthquake loading)