Satisfied customers are our best recommendation! Here you will find a selection of our projects, which reflect the comprehensive range of services of MF Engineering.
New development of steel structures for the disassembly of the bottom part (243 t) of the reactor pressure vessel
Setting down (243 t) of the reactor pressure vessel in the fuel element storage pool
New development of a modular steel hall for containment of the demolition work area
Alteration of a working platform for the dismantling of the insulation in the reactor pit with a robot, Construction of a mock‑up as testing station for the removal of the insulation
Reinforcement of a skirt support for the bottom part (85 t) of a reactor pressure vessel as well as a turning frame for its spherical cap (26 t)
Fabrication and assembly of a lifting system for the disassembly of the reactor pressure vessel
Change of the dissection concept for a steam generator
Fabrication of a working bridge for the dismantling of contaminated components
Disassembly and decontamination of the dished end with a weight of approx. 48 t
Proof of an existing reinforced concrete structure under loading with a crane and strand jacks (ca. 220 t)
New development of steel structures for the disassembly of several steam converters (each about 170 t)
Proof of an existing structure of reinforced concrete under loads due to a crane and stand jack facility (approx. 200 t), retrofitting of the concrete ceiling with CFK lamination
Take-down of a main pipe (9,2 t) for a Separator / Heat-Exchanger in Switzerland
Fabrication of a turning frame for the dismantling oft he lower part (42 t) of the reactor pressure vessel
Check of the existing reactor building crane under the load of the steam generator to be disassembled (360 to and 300 to)
Disassembly of the reactor building crane girders